Let me first say, kudos to Omnigroup for such a great product!
Now, I am somewhat new to Omniplan so I am sure these topics have already been covered but I could not find a good up-to-date answer.
1) I have several tasks (call them tasks 1-5) that are prerequisites to critical path tasks yest these tasks (1-5) are not showing up on the critical path. The tasks are driven by constrains (so I have not set the dates explicitly). As a test, if I change the duration of the want-to-be critical path tasks, they drive out the end date and all tasks on the critical path. So I think they are linked correctly, but they are not highlighted on the CP.
2) I am running version 1.6.3 and was curious if the feature to display task dates we incorporated a this point. If not, this is a must have. Otherwise, there is the need to constantly scroll up to the date headers and try to line up the tasks with the date.
Thanks for any help!
Now, I am somewhat new to Omniplan so I am sure these topics have already been covered but I could not find a good up-to-date answer.
1) I have several tasks (call them tasks 1-5) that are prerequisites to critical path tasks yest these tasks (1-5) are not showing up on the critical path. The tasks are driven by constrains (so I have not set the dates explicitly). As a test, if I change the duration of the want-to-be critical path tasks, they drive out the end date and all tasks on the critical path. So I think they are linked correctly, but they are not highlighted on the CP.
2) I am running version 1.6.3 and was curious if the feature to display task dates we incorporated a this point. If not, this is a must have. Otherwise, there is the need to constantly scroll up to the date headers and try to line up the tasks with the date.
Thanks for any help!