I am planning a construction job. Most tasks require two or more people (e.g., because one person cannot lift something by himself). I have assigned several tasks to both A and B. A is taking vacation all of October. After I level resources, I see that OmniPlan has scheduled some of these tasks in October, assigning the work entirely to B and doubling the duration.
Instead, I want these A and B to cooperate on these tasks, each contributing half the total effort. No task should be scheduled for October. How can I make this happen?
Instead, I want these A and B to cooperate on these tasks, each contributing half the total effort. No task should be scheduled for October. How can I make this happen?