Is there are way to set up a connection between a task and a milestone so that when the milestone moves (say a day later) the connected task moves (a day later)? I need a task to happen the day before a meeting so if the meeting moves, I want the task to move automatically with it. Is there a way to do that?
 
To do this, hover your mouse cursor over the milestone in the gantt chart, then click and drag an arrowhead from the beginning of the milestone to the beginning of the task. Then, select the milestone and bring up the "Task : Dependencies" inspector and enter a lead time of -1d.

When you drag a milestone now, it should bring the task along with it.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't Move / Adjust tasks - help! [A: Spotify, VLC, & Rdio for Mac interfere with the mouse] tonyg0192 OmniPlan General 12 2013-01-22 06:18 PM
Can't move/copy tasks between docs workinprogress OmniPlan General 2 2011-07-27 12:49 PM
How to move PalmOS tasks/memos to OmniFocus sderose OmniFocus for iPhone 0 2008-09-11 10:02 AM
Tasks complete/ part complete move to start of project? Omni User OmniPlan General 1 2008-06-16 11:08 AM
How to move a group of tasks? plexus OmniPlan General 1 2006-10-10 04:49 PM


All times are GMT -8. The time now is 07:59 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.