7.5hr day still results in 8hr default tasks Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi All,

I'm hoping there's an easy solution to this:

My organisation uses a 7.5 hour working day, so I've changed both the Normal Working Week and the Project: Unit Conversions data from the default 8 hour working day to use 7.5 hours.

However when I enter a task, its default duration is 1 day 0.5 hours, e.g. it is still using the default 8 hour working day settings.

Can this be adjusted? Any tips appreciated!

Cheers,
Alex
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Repeating projects and default tasks? nielsk OmniFocus 1 for Mac 4 2010-12-31 01:00 PM
Repeating tasks and default time Sandpiper OmniFocus 1 for Mac 7 2008-08-20 11:14 AM
Feature request - default insert location for new tasks dondo OmniFocus 1 for Mac 0 2008-07-21 10:32 AM
OmniFocus: Querying tasks in Applescript gives odd results RobTrew AppleScripting Omni Apps 0 2008-03-01 01:03 AM


All times are GMT -8. The time now is 03:00 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.