I am planning a project whereby the company works 5 days a month on the project. Despite setting the day to 8 hours, and the month to 40 hours, the gantt shows many many more than 5 days worth of tasks starting at the same time, on day one.

Is there a way of telling the gantt to only allocate 5 days per month, and then move tasks to the next in order of priority and dependencies?

Thanks
 
In the calendar view, you can specify which days are actually working days for this project. Then OmniPlan will only schedule tasks on those days.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Month-based planning micrology OmniPlan General 0 2013-01-04 12:34 PM
Planning actions over a few days kenoli OmniFocus 1 for Mac 8 2011-05-07 10:38 AM
Month-Based Planning with Undetermined Start Date: Formatting and Effort Calculation DavidS OmniPlan General 0 2011-01-02 07:35 AM
Going to Seattle for three days in the coming month. dude Omni Lounge 2 2010-10-17 08:18 PM
Feature Request - Move "X" Number of Days CorgiGirl OmniFocus 1 for Mac 15 2009-04-02 08:36 AM


All times are GMT -8. The time now is 05:50 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.