Task bar display on non-working days Thread Tools Search this Thread Display Modes
Hi Forum,

I have searched the manuals and the OmniPlan General forum before posting this, so apologies if the answer is here somewhere.

I have a project where the resources only work on one day per week. On one of those days nobody is available, and the bar for a task spans across from the last working day to the next working day, giving the initial impression that there is work happening that day (although inspection of the properties reveals the truth).

I would like a different display for a bar that crosses non-work time (something like what can be seen in http://forums.omnigroup.com/showpost...37&postcount=1), and I could have sworn that there was a way.

Can anyone enlighten me?

Jon
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
See for each task, which days I have worked on it or not hefe_weizen OmniPlan General 0 2013-01-05 02:48 AM
How to ensure a task is not split between days? hmtucaz OmniPlan General 2 2012-06-19 03:37 PM
Prevent a task from splitting over two days breddels OmniPlan General 0 2011-04-01 01:36 AM
Working 7 days per week Allrad OmniPlan General 1 2010-05-24 03:59 PM


All times are GMT -8. The time now is 11:38 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.