I've created an extensive plan and assigned resources when the resources had a default of 100% units. I now need to change that percent to 90%. How do I do this globally without having to reassign each resource or manually editing each task?
Note what I'm talking about is initially I had resources at 100% units and I assigned them to different tasks. I then edited the global default for each resource to 90% using the resource editor but when I level the plan I get violations. I'm hoping there is a quick and efficient way for me to have all the assigned resources units changed to 90% and then level the plan using the new resource global unit percent (90%).
Note what I'm talking about is initially I had resources at 100% units and I assigned them to different tasks. I then edited the global default for each resource to 90% using the resource editor but when I level the plan I get violations. I'm hoping there is a quick and efficient way for me to have all the assigned resources units changed to 90% and then level the plan using the new resource global unit percent (90%).
Last edited by wfiveash; 2010-11-03 at 02:42 PM..