Please advise:

I get my developers to submit project plans as csv files, using a template we created by exporting a boilerplate Omniplan project.

Then I import the csv file, and everything works fine - complete with task groups, assignments, duration and dependencies.

Then I copy all tasks under a group task created in the masterplan - everything copies, except the "Assigned" column - which means I have to enter the assignments manually - the resource names are spelt identically - what am I missing?

I've also tried copying the tasks to a new, blank project file - assigned resources still don't copy across!?
 
Quote:
Originally Posted by gemello
Please advise:

I get my developers to submit project plans as csv files, using a template we created by exporting a boilerplate Omniplan project.

Then I import the csv file, and everything works fine - complete with task groups, assignments, duration and dependencies.

Then I copy all tasks under a group task created in the masterplan - everything copies, except the "Assigned" column - which means I have to enter the assignments manually - the resource names are spelt identically - what am I missing?

I've also tried copying the tasks to a new, blank project file - assigned resources still don't copy across!?
Sorry for taking so long to reply. On our new 'OmniPlan Extras' page, we've put up an Applescript that allows you to copy tasks and their assignments from one project to another. Here's the link: OmniPlan Extras
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
All new tasks assigned to same project? Jpearson OmniFocus for iPad 3 2011-12-01 02:32 PM
Show assigned to group tasks GuyO_2009 OmniPlan General 0 2009-10-01 07:55 AM
Export lists of tasks assigned to someone Owen Linzmayer OmniPlan Extras 8 2008-09-04 03:14 PM
Task Costs With Multiple Assigned Resources dmabram OmniPlan General 1 2008-03-13 12:48 AM
Assigned Resources valsjo OmniPlan General 0 2007-10-28 01:26 PM


All times are GMT -8. The time now is 07:14 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.