Perhaps I do not understand the distinction between effort and duration.
I have a task that lasts, say, 1 hour, but the assignee can take up to a week to complete the task.
1) Is this the correct way to distinguish effort (the 1 hour) from duration (the week)?
2) In OmniPlan for iPad, can effort and duration be disconnected? (They are locked to equal values now.). How can you disconnect them?
Many thanks!