The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
How to ensure a task is not split between days? Thread Tools Search this Thread Display Modes
I am scheduling a task (a phone conference) that is expected to last two hours. Right now, based on prior tasks, it shows as starting during the last work hour of one day, and continuing over to the first work hour of the next day. The call cannot be done that way. It needs to be done in a 2-hour period, not 2 different 1-hour periods.

Any advice on how to accomplish that?
 
I haven't found a built-in mechanism you could use for that without some fiddling. I would suggest laying out your plan, finding the date on which the task ends, and then applying a start and end constraint to the task to force the start and end to both be on that date.

 
Thanks. That will do the trick.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Split task or group? amarkelo OmniPlan General 2 2013-04-01 05:08 PM
Split task mikekutz OmniPlan General 2 2012-10-31 09:59 AM
What is a Split Task joelande OmniPlan General 0 2012-03-16 01:53 PM
How do you unsplit a split task? yahoo160 OmniPlan General 3 2012-02-10 02:50 PM
Split a task in some hours per day lollo17 OmniPlan General 0 2011-04-22 08:01 AM


All times are GMT -8. The time now is 07:08 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.