How do folks handle due dates on critical path tasks that are delaying a project. That is, they don't have a particular due date, but each day they go undone, a whole project will be delayed.
I have fallen into the trap of setting arbitrary due dates for those items, but as we all know, that ends up deteriorating the usefulness of the due date system in Omnifocus. I save due dates for items that are truly due now.
So, how to note those tasks that are holding up whole projects but aren't actually due at any particular time?
Thanks,
Mike
How do folks handle due dates on critical path tasks that are delaying a project. That is, they don't have a particular due date, but each day they go undone, a whole project will be delayed.
I have fallen into the trap of setting arbitrary due dates for those items, but as we all know, that ends up deteriorating the usefulness of the due date system in Omnifocus. I save due dates for items that are truly due now.
So, how to note those tasks that are holding up whole projects but aren't actually due at any particular time?
Thanks,
Mike