I'd like to have some advice on how to achieve the following:

In a simple project, there are 2 tasks, each taking 3 days of work.
There is only 1 resource, which is assigned to the 2 tasks.

After assigning, the resource is overallocated (200%) so I have to level the project.

The result is that the first task in my list will be handled before the second task giving my resource 6 days of work. The first 3 days on task #1 and the following 3 days on task #2

My question:
How can I obtain that my resource will work on BOTH tasks for 50% during 6 days?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Automatically assign a resource to new tasks? psidnell OmniPlan General 2 2012-03-28 10:09 PM
Mixed units for durations SteveH OmniPlan General 3 2011-08-20 08:59 AM
Mixed midpoints? macktheturtle OmniGraffle General 1 2007-05-27 03:47 PM
Moving tasks in resource view...? jdrogers@mac.com OmniPlan General 1 2007-01-08 04:37 PM


All times are GMT -8. The time now is 07:33 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.