Assigning multiple resources at 100% each. Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi there,

Apologies for a bit of a newbie question: I want to be able to assign more than one resource, at 100% on a single task. This is because I don't want to split a single task into three separate ones for each resource.
I'd rather have a single task with three resources and a single cost calculated from that.

Any ideas?

Thanks


David
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to Balance Resources Among Multiple Projects Xyzwolf OmniPlan for iPad 2 2012-07-17 03:35 AM
How to require multiple resources at the same time? elj OmniPlan General 1 2012-03-27 11:33 AM
multiple projects with staff resources richmond OmniPlan General 95 2011-11-18 01:50 AM
Task Costs With Multiple Assigned Resources dmabram OmniPlan General 1 2008-03-13 12:48 AM
Bug: Assigning partial resources ajrichardson OmniPlan General 2 2006-08-01 01:23 PM


All times are GMT -8. The time now is 08:41 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.