My question is related to rescheduling a group of tasks.
I created a reasonably complex task structure and grouped tasks in groups.
When I try to reschedule a group of tasks by changing the group attributes in the inspector, it changes start and end dates for the group only, not for the underlying tasks. How can I move the whole group of connected tasks in time? It will take me otherwise a day to move them and their dependances individually one by one.

Thanks!
Yuri
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Flagged - group tasks cbeaudj OmniFocus 2 for Mac (Private Test) 2 2013-05-14 11:46 AM
Group Tasks amitsbajaj OmniFocus 1 for Mac 2 2013-02-14 08:41 AM
Backdating completed tasks (esp. after rescheduling/leveling) omnibob OmniPlan General 1 2013-02-08 08:34 PM
Show assigned to group tasks GuyO_2009 OmniPlan General 0 2009-10-01 07:55 AM
How to move a group of tasks? plexus OmniPlan General 1 2006-10-10 04:49 PM


All times are GMT -8. The time now is 11:30 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.