Hi,
When I flag the checkbox in the leveling menu : Don't schedule any task before date : 09/09/11 - which is tomorrow in this case. Omniplan does level some tasks to start BEFORE the 9th of September. He schedules them even to the 7th of September (which was yesterday in this case). How can this be ?
I am doing something wrong ?
Please advise,
When I flag the checkbox in the leveling menu : Don't schedule any task before date : 09/09/11 - which is tomorrow in this case. Omniplan does level some tasks to start BEFORE the 9th of September. He schedules them even to the 7th of September (which was yesterday in this case). How can this be ?
I am doing something wrong ?
Please advise,