Cost of Project: discrepancy Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi, I have a problem with the project cost and it would be great if someone could help with my headache!

I have added the resource costs for each task separately under Inspectors >Task information. Note: not all of my tasks in the project bear cost.

When I highlight the entire project in the outline view and then go: Inspectors>Task information: cost, the total value of the project is 28k but when I export the same plan into HTML and upload it onto the server, the cost of the project displays as 65k.

I have been through all project's tasks separately and manually checked that in Inspects>Task: information, only the tasks that do bear costs have cost assigned to them.

Still, the total value of the project varies when looking at online and offline version.

Is there anywhere else that I should be checking the total project cost?

Many thanks for any suggestions
K.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource/Project Cost Per Month/Phase ketjak OmniPlan General 5 2011-10-18 01:55 PM
Size discrepancy WITHIN diskSweeper cayleyrice OmniDiskSweeper 2 2011-08-23 05:04 AM
YOUR GUESS: How much it will cost vs. how much it should cost? doodiebrad OmniFocus for iPad 40 2010-07-27 06:41 AM
Due date display discrepancy Toadling OmniFocus 1 for Mac 1 2008-10-23 02:25 PM
Discrepancy in settings on iPhone app ext555 OmniFocus for iPhone 0 2008-09-22 01:35 AM


All times are GMT -8. The time now is 01:38 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.