I need to change when the weekends are in my Omniplan from Saturday/Sunday to Friday/Saturday. It is currently not letting me assign tasks on my work week of Sun-Thur, it will not let me assign a task on Sundays?

So, how do I change the actual work week from Mon-Fri to Sun-Thr?

Thanks!

lance
 
First, go to the calendar view, select the Normal Work Week for Project setting at the lower left, and adjust the display on the right to show the dates and hours of a normal work week for this project. You can also do this on a per-resource and per-date basis to account for vacations, different schedules, etc.

Now when you level the project the dates should reflect your newly set schedule. See the attached example.
Attached Thumbnails
Click image for larger version

Name:	Set normal work week.png
Views:	870
Size:	60.2 KB
ID:	1032   Click image for larger version

Name:	Example project.png
Views:	699
Size:	53.7 KB
ID:	1033  
 
That did it, thanks so much! Omniplan rocks :)

lance
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
where are the weekends? OmarKN OmniPlan General 4 2012-10-10 09:31 AM
Highlight Weekends noisebug OmniPlan General 1 2010-03-31 05:39 PM
Can not show weekends..? niels.henrik OmniPlan General 8 2008-03-10 05:00 PM
Including weekends in the project? FlyingBarney OmniPlan General 1 2007-05-12 08:52 AM
Work on weekends Fake OmniPlan General 2 2006-08-08 12:54 AM


All times are GMT -8. The time now is 07:38 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.