The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan for iPad
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
How to change the start of a project Thread Tools Search this Thread Display Modes
Hello All,

I'm trying to change the start date of a project, if I do it the usual way the timeline view accommodate the request but the tasks stay the same.
In other words, I set the start project on Sep 17, now I would like to change it to September 1, and want the tasks chane as well accordingly (means the first task starting on Sep 1), what I should do?

Thanks for any help

Regards

Teo
 
Try setting all of your tasks to ASAP (As Soon As Possible) in the Task Inspector > Task Info tab > Direction.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Change action to project possible SerenusZeitblom OmniFocus 1 for Mac 3 2013-08-06 11:47 PM
Any way to change date/time format in Start and End columns? jseverino OmniPlan General 1 2013-02-06 03:27 PM
Can't change the start & End dates tarekag OmniPlan General 2 2011-08-04 08:55 AM
Change Project start date? paulriedel OmniPlan General 2 2009-12-09 01:55 PM
How do you change an action into a project? Flexattend OmniFocus 1 for Mac 3 2009-10-24 11:03 AM


All times are GMT -8. The time now is 12:22 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.