Using due dates is this possible? Thread Tools Search this Thread Display Modes
Garbage is collected on friday. I put it out on thursday. I enter 'take out garbage' for the next thursday, and set it to repeat every week. That works, however, once I check off that I took out the garbage, a new 'take out garbage' is created.

Even though I don't want to take out the garbage until the next thursday, that task is shown as available for the entire week. I understand why this happens, but it doesn't really work for this type task.

I thought of giving it a 'start date' of thursday, but then it doesn't pop up as due.

Is there anyway do accomplish what I'm trying to do? Would setting a start date and due date as both that thursday cause the task to only be shown available on thursday?

Any help is much appreciated.
 
Quote:
Originally Posted by gary View Post
Garbage is collected on friday. I put it out on thursday. I enter 'take out garbage' for the next thursday, and set it to repeat every week. That works, however, once I check off that I took out the garbage, a new 'take out garbage' is created.

Even though I don't want to take out the garbage until the next thursday, that task is shown as available for the entire week. I understand why this happens, but it doesn't really work for this type task.

I thought of giving it a 'start date' of thursday, but then it doesn't pop up as due.

Is there anyway do accomplish what I'm trying to do? Would setting a start date and due date as both that thursday cause the task to only be shown available on thursday?

Any help is much appreciated.
You've got all the pieces! Set a start date for Thursday morning. Set a due date for Thursday night. Repeat every 1 week.
 
Cool. Thanks. Just wanted to make sure I wasn't barking up the wrong tree :)
 
By the way, you can test out what will happen in these scenarios by completing actions by typing a date/time into the completed field in the inspector. Doing so makes the program behave as if you had checked the completion box at the date/time specified.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Assign Project Due Dates Without Action Due Dates Revearti OmniFocus 1 for Mac 8 2014-05-12 04:58 AM
Start Dates-Due Dates and iPhone behaviour glen.saberton OmniFocus for iPhone 4 2013-03-19 02:24 PM
Advice on due dates versus start dates Ed P OmniFocus 1 for Mac 4 2012-03-18 07:58 AM
Basics ? Project Dates vs Action Dates amg OmniFocus 1 for Mac 7 2009-04-16 12:13 PM
context view using start dates vs. due dates bpwhistler OmniFocus 1 for Mac 6 2008-11-20 03:52 AM


All times are GMT -8. The time now is 04:39 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.