Hi there
I'm a bit new to this so excuse me if I'm doing something wrong - (I guess who isn't new to this iteration!).
Anyhow - I have a task that I'm trying to schedule - both by moving the handles on the task in the chart and in the inspector - but for some reason it keeps skipping from 2am to 12 noon ands I want the task to start at 11am.
My calendar has three 'normal hours' time blocks - 12 Midnight to 2.30am, 11am until 7pm and 8.30 pm until 12 midnight.
Any thoughts?
Thanks in advance
David
I'm a bit new to this so excuse me if I'm doing something wrong - (I guess who isn't new to this iteration!).
Anyhow - I have a task that I'm trying to schedule - both by moving the handles on the task in the chart and in the inspector - but for some reason it keeps skipping from 2am to 12 noon ands I want the task to start at 11am.
My calendar has three 'normal hours' time blocks - 12 Midnight to 2.30am, 11am until 7pm and 8.30 pm until 12 midnight.
Any thoughts?
Thanks in advance
David