I can't figure this out. If I schedule my project forward from a fixed start 12/10/12, it ends 1/25/13. However, I really want to launch on 1/28/13 and push things back a bit. I figure that scheduling backward from a fixed end (1/28/13) is what I should do. However, when I change the project to this setting, the project creates a violation and the project ends on 2/11/13. For some reason it pushes back the project start date to 1/7/13. I don't have any constraints and it shouldn't be a resourcing issue.
Anyone have thoughts on what is happening?
Anyone have thoughts on what is happening?