Omniplan - task, team of workers, cost Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
You can speed things up by making the default setting for new tasks be set up as "fixed duration" tasks. To do this, create a new task and change its setting to fixed duration and while the task is still selected, go to "Project" > "Set as Default for New Tasks". Now, ever task that you create will automatically be set to fixed duration.

To speed up the assignment part, you can select multiple tasks and go to the "Task : Assignment" inspector. As you check each resource it will be assigning them to all the tasks in your selection.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Total cost on task bars in GANT view etvaxed OmniPlan General 1 2012-02-21 06:27 AM
One task, three resources, how do I get an accurate total cost? jimantonopoulos OmniPlan General 1 2011-04-18 10:49 AM
Task Cost field sschiff OmniPlan General 1 2008-08-21 12:32 PM
Showing total resource cost for task groups? docswab OmniPlan General 4 2007-01-04 04:03 PM


All times are GMT -8. The time now is 10:32 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.