The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Showing total resource cost for task groups? Thread Tools Search this Thread Display Modes
How do I view the total resource cost for all the child resources contained in a Task Group?

If this is not possible now, it seems like an important feature to add ASAP.

Thanks,
Steve
 
You can turn on the cost columns by going to "View" --> "View Options" in the menubar and checking the "Resources Cost", "Total Cost", and "Task Cost" boxes.
 
Thanks for your speedy reply. I had found it myself and tried to post my own reply, but it must not have been saved.

I appreciate Omni's great support.

Steve
 
just started w/ the product....having some issues getting my numbers to add up with multiple resources on a task at different rates...
 
mysvcmon: Could you please provide a specific example?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Total cost on task bars in GANT view etvaxed OmniPlan General 1 2012-02-21 06:27 AM
One task, three resources, how do I get an accurate total cost? jimantonopoulos OmniPlan General 1 2011-04-18 10:49 AM
Resource cost over time? sshorter OmniPlan General 1 2007-08-08 11:53 AM
Total Cost for a Resource HunterBoss OmniPlan General 6 2007-07-13 02:01 AM
Total Cost blank if assign task to resource group. gregc OmniPlan General 2 2007-02-06 11:15 AM


All times are GMT -8. The time now is 10:18 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.