Doesn't seem to be taking availability of equipment into account Thread Tools Search this Thread Display Modes
I'm trying to put a test plan together; in order to do my testing, I need access to specific hardware, which I'll only have a few days a week. So I tried defining a piece of equipment for each piece of hardware, and changed its availability to only two days a week. But leveling doesn't seem to be taking account of this; tasks are still getting placed on days that the equipment isn't defined as being available.

I should say that, in terms of what I'm trying to do, the specific days don't really matter; I only actually care about a week level view, knowing that I'll only have access to a given system say 40% of the time. As is, though, I'll have tasks placed on all five days in a week, which isn't helpful.

Thanks.

Kevin McKenzie
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Leveling with unavailable equipment slondike OmniPlan General 0 2011-02-08 05:28 PM
Understanding the Availability Filter denrael Applying OmniFocus 1 2011-01-26 11:27 PM
Equipment is still influencing duration? michaelaye OmniPlan General 4 2010-07-05 01:02 AM


All times are GMT -8. The time now is 06:55 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2020, vBulletin Solutions, Inc.