Can actual timeline be moved to baseline? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
[ SORRY! Misposted in Outliner forum... Picked wrong week to give up caffeine... ]

This may not actually be a problem, but I think it is. What I did was work up a timeline (gantt chart) in the "Actual" mode or view, rather than "Baseline" as I think you're supposed to do.

If I should have been in "Baseline" mode or view while sketching out the timeline, how do I move this timeline from "Actual" to "Baseline". Copy and paste only takes the textual outline structure, not the rest.

Thank you!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Timeline tool dfclark OmniGraffle Extras 14 2013-03-22 11:28 AM
Faux pas - Can I change actual to baseline? simmonet OmniPlan General 4 2012-04-28 02:51 PM
Omnifocus for Mac timeline GeoffAirey OmniFocus 1 for Mac 3 2010-09-30 04:17 AM
OF 2.0 timeline? ToddPeperkorn OmniFocus 1 for Mac 1 2009-10-25 06:01 AM
Moved Downloads terriyaki OmniWeb Feature Requests 0 2008-06-12 11:03 AM


All times are GMT -8. The time now is 09:14 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.