Being not-too-experienced with typical PM tasks I'm not certain if what I'm trying to accomplish here can be done with two simple tasks or not..
I have a resource who's got a development task to work on which has his attention for 100% of the time, and will take several days. In the middle of that time there's a deployment task with a fixed start/end time that he needs to be involved with that will take up 100% of his time for its duration.
I was hoping I could convince OmniPlan to overlap the two tasks, and extend out the completion date of the longer task, but I'm not sure what things to tweak to accomplish that, or if it's even possible. Will I have to split the longer task into phases that fit on either side of the task with the fixed date, similar to this thread (http://forums.omnigroup.com/showthread.php?t=16893) or can I actually get the two tasks to overlap?
I have a resource who's got a development task to work on which has his attention for 100% of the time, and will take several days. In the middle of that time there's a deployment task with a fixed start/end time that he needs to be involved with that will take up 100% of his time for its duration.
I was hoping I could convince OmniPlan to overlap the two tasks, and extend out the completion date of the longer task, but I'm not sure what things to tweak to accomplish that, or if it's even possible. Will I have to split the longer task into phases that fit on either side of the task with the fixed date, similar to this thread (http://forums.omnigroup.com/showthread.php?t=16893) or can I actually get the two tasks to overlap?