I have a question about resource assignment for a task.

Lets say I have a task called Painting and its effort is 1 day. I have two workers both working only between 8 am - 12 am. This, I set up in the Calendar view. The Normal week for the project though is 8am-12am, 1pm-17pm.

Now I choose the task in Task View and assign the first worker to the task. In the Gant view I can see that the Duration goes from 1d to 1d 4 h.

When I assign the next worker also to the task I can see that the Duration remains 1d 4h.

I think this is strange. I have grayed out Duration so that it should not change (the two heads grayed out).

I thought that Duration should not change even if I assign it to a person working only half a day.

Perhaps I'm missing something?

/rob :-)
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
All new tasks assigned to same project? Jpearson OmniFocus for iPad 3 2011-12-01 02:32 PM
Task Costs With Multiple Assigned Resources dmabram OmniPlan General 1 2008-03-13 12:48 AM
What's an Assigned Date? Shotster OmniFocus 1 for Mac 13 2007-12-02 11:53 AM
Updating assigned units vil OmniPlan General 1 2007-11-06 09:55 PM
Copying tasks across files - assigned resources lost? gemello OmniPlan General 1 2007-05-01 01:08 PM


All times are GMT -8. The time now is 03:47 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.