How do I get OmniPlan to total hours? Thread Tools Search this Thread Display Modes
I have the task and resource information input to the project. After leveling, how do I determine total project hours and total hours for each resource?

-SMJ
 
Go to the Resource View and go to "View" > "View Options", then check the "Total Hours" column on. That will show the total hours per resource.

To find out the total project hours, click on the text at the bottom of the OmniPlan window to the right of the plus and minus buttons.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
New to OmniPlan, off hours question Newcastle OmniPlan General 3 2011-08-26 02:20 PM
View "Total Hours" in units of "hours" pheller OmniPlan General 4 2009-11-17 01:37 PM
Total number of rows? Armanini OmniOutliner 3 for Mac 3 2007-06-19 11:51 AM


All times are GMT -8. The time now is 10:26 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.