3 resources are assigned to complete a task with a total time of 26 hours.

Do I have to add 3 resources and separate them out (2x8 hours + 1 x 10 hours)?

All 3 resources do the same job each week.

Thanks
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed Cost, Fixed Duration, Flexible Effort/Resources metasim OmniPlan General 2 2012-02-03 04:24 PM
Effort adjustor KlassicJazz OmniPlan General 0 2011-01-09 08:06 AM
jungledisk redux kingsinger OmniFocus Syncing 0 2008-08-28 01:37 PM
Spread effort based on duration and total effort Hap OmniPlan General 1 2007-02-14 04:50 PM