I have three main "projects" set up in my file.
1) personal
1.1) landscape yard
1.1.1) find lot lines
1.1.2) sketch yard
1.1.3) etc.
1.2) clean attic
1.2.1) etc.

2) freelance
2.1) client 1
2.1.1) job 1
2.1.2) etc
2.2) client 2
2.2.1) job 1
2.2.2) etc.

3) work
etc.

Can I have my landscape job just be the weekends?
Can I have my freelance work just be the evenings?

I am trying to put all my "projects" into Omniplan so that I can map out how much actual time they take up - if I need more resources and when I might actually be done and not overschedule.

think of it as a GTD personal productivity with gantt charting. <<grin>>

Thanks
 
If there is no shared timelines between the projects, it's probably better to put them in seperate projects with each having the resources limited to the times you described. Since one project is just weekends & the other is just weekdays, this is fine. Alternatively in a single project file, you could setup duplicate resources like Me (Weekday) & Me (Weekend). Then setup distinct schedules for each of those resources.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] chaloum OmniPlan General 11 2013-07-05 12:23 PM
Employee Shift Work Schedule powerpaul OmniPlan General 2 2012-11-08 08:28 AM
New task without any schedule Maxi OmniPlan General 0 2011-04-15 06:06 AM
FR: Tasks repeat/recur on work week schedule dbyler OmniFocus 1 for Mac 6 2010-08-28 08:11 AM
Bug: Problem with changing work schedule abusch OmniPlan General 2 2006-08-02 10:37 AM


All times are GMT -8. The time now is 02:09 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.