leveling for non-fulltime resources? Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
Hi everyone,

I have seen multiple forum posts with questions about leveling and units < 100%, but haven't found the answer I was looking for. I am using Omniplan 2.1.2.

My example:
- two tasks: Start (1d) and Finish (6d)
- resource group "my team" with John and Mary
- resources are set to "keep effort fixed"
- the team works part-time (50%)
- I assign the tasks to "my team"

To specify the resources are working part time, I have set their units to 50%.
They don't have fixed schedules, all I know is that they work 20 hours a week.

When I level my project, each task is done both by John (50% of 50%) and Mary (50% of 50%).

This is not what I expect. I would expect only one person to work on the task, and automatically adjust the duration if necessary.

Any suggestions?
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Untitled task in resources view after undo leveling luke18 OmniPlan General 4 2011-09-08 10:11 AM
I just don't understand leveling and <100% resources schmidt4brains OmniPlan General 6 2010-06-20 08:50 AM
Leveling leaves resources overused granerw OmniPlan General 4 2008-02-27 09:49 PM
Leveling resources connie OmniPlan General 1 2006-08-22 05:10 PM


All times are GMT -8. The time now is 04:22 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2019, vBulletin Solutions, Inc.