I'm sure I'm doing something stupid...
I'm trying to level some tasks that are assigned to an equipment resource (1 unit, 100% efficiency). I've set the resource's work schedule so that it is unavailable until April 9, but when I level the tasks they are placed starting at Mar 13. What am I doing wrong? Do equipment resources have different rules about their work schedules than people?
Thanks for any help
I'm trying to level some tasks that are assigned to an equipment resource (1 unit, 100% efficiency). I've set the resource's work schedule so that it is unavailable until April 9, but when I level the tasks they are placed starting at Mar 13. What am I doing wrong? Do equipment resources have different rules about their work schedules than people?