I am trying to plan a project that has a team in the office which works & bills a 5 day week, and a team in the field which works and bills a 7 day week. Office and field tasks occur simultaneously.

I am aware that I can set the working week for the whole project via Calendar view, but what I want to do is set the working week for particular tasks.


Is this possible?


Many thanks

jim
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes



All times are GMT -8. The time now is 02:01 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.