Hi All,

Apologies if this has been answered already elsewhere. Is there a way to set a task dependency (or, more appropriately, constraint) whereby a task cannot start until a preceding task reaches X% completion?

Essentially I have a situation where I have task2 dependent upon task1 (theoretically), however work may actually commence on task2 provided that task1 has reached a minimum of 75% completion. Needless to say, task 2 cannot end prior to task1 completion, of course.

Is there a way to do this?

Thanks in advance,


Leland
 
Nothing built-in, but you could split task1 into task1a and task1b, with a F->S dependency from task1a to task2 (and one to task1b) and a F->F dependency from task1b to task2. Tasks 1a and 1b would be 75% and 25% of the length of the original task1.
 
hm... I had considered that, but it's ugly (visually)... but I guess it's a suitable work-around for now.

Something to add to the wishlist, perhaps?

Leland
 
Use Help->Send Feedback to make a feature request.
 
lelandv and I discussed this on twitter earlier but you can set a -25% lead time in the "Task : Dependencies" inspector.
 
Yup.. thanks.. I confirm it works! (Also confirmed on Twitter by @OmniPlan as well)

Wasn't sure if there would be some inadvertent [unwanted] workflow implications, but seems okay.

Thanks a lot!

Leland
 
Done in by the manual once again...only the online help glossary reveals the percentage trick. Good to know, although I bet absolute lead times are far more commonly used.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Query based on completion date cdavaz OmniFocus 1 for Mac 3 2012-07-17 09:20 AM
howto: date AND time via email Vlad Ghitulescu OmniFocus 1 for Mac 0 2011-04-30 12:20 AM
Due Date Deletion Triggers Completion EricW OmniFocus 1 for Mac 0 2008-02-19 02:04 AM
Date of Completion? dhm2006 OmniFocus 1 for Mac 2 2007-07-18 08:33 AM
Address completion by date? ata OmniWeb Feature Requests 4 2007-02-17 10:07 AM


All times are GMT -8. The time now is 05:06 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.