Hi Omniplan guru's -

I need to create a dependency or constraint that is:

"Task A" must complete before "Task B".

Understand... I'm NOT asking for "Task B" to start after "Task A".

How would I do this?

Thanks,
Thomas.
 
That sounds to me like you want a Finish->Finish dependency. Task B will not finish until Task A has finished, but can be active before Task A has finished.

Click and hold on the Connection button in the toolbar to get the drop-down menu, then select Finish->Finish. Or drag a dependency line from the lower-right corner of Task A on the Gantt chart to the upper right corner of Task B. Or type it into the dependencies column in the outline, if you have that visible.
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can't change date for task started before today? [A: Remove constraint in Task:Schedule inspector] chaloum OmniPlan General 11 2013-07-05 12:23 PM
Simple Applescript, Create Task, Assign resource, Assign dependency dexterama OmniPlan Extras 2 2012-11-18 12:25 PM
Start Constraint Question MacDork OmniPlan for iPad 1 2012-06-09 09:33 AM
BUG: WBS view Constraint Star/End will not clear stephenrussett OmniPlan General 3 2010-02-15 09:09 PM
Define constraint as a function of another task? juliabell OmniPlan General 1 2009-09-12 09:30 PM


All times are GMT -8. The time now is 01:44 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.