How do you set OmniPlan to use a generic calendar instead of specific calendar dates? I don't know the start date for a project (it will start whenever it's approved), so I want to show "week 1," "week 2," etc. Is there a way to set this? I couldn't find it, and I'd appreciate a pointer. I'm running version 1.7, if that makes a difference.

Thanks!
Emma
 
Bring up the Project: Information inspector with Inspectors->Project (or command-4). Click on the little suitcase icon to get the Project: Information panel and click the radio button next to Start: Undetermined Date as seen in the attached image.
Attached Thumbnails
Click image for larger version

Name:	Screen shot 2012-02-16 at 5.37.27 PM.png
Views:	675
Size:	22.9 KB
ID:	2264  
 
Thanks! That was exactly what I needed.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
iCal Publishing and Due Dates > 2 Weeks Away joncgde2 OmniFocus 1 for Mac 5 2011-10-23 08:40 PM
How to create a swimlane diagram that is not linked to specific dates? skippingrock OmniPlan General 0 2011-04-01 11:29 AM
Ability to show time in "in three weeks, in two weeks, tomorrow" formats mr_projects OmniPlan General 1 2007-11-02 11:28 AM


All times are GMT -8. The time now is 12:07 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.