Hi all,

I am testdriving OmniPlan after Merlin drives me nuts not being able to import MPP files properly, which worked fine so far in OmniPlan.
But I found that adding equipment to a task reduces it's duration, which should not happen.
How can I add equipment to a task without influencing the duration, but to be respected at levelling to avoid double booking of the equipment?

This to me seems like the most important task a scheduling tool should be able to do, no?

Best regards,
Michael
 
You can set up equipment resources to not reduce a task's duration by selecting the equipment resource in the Resource View, then going to the "Resource : Information" inspector. From there, you can set the efficiency to 0%. That should stop equipment resources from reducing the duration of a task.
 
Thank you, works as advertised. Exactly what I need for now.
 
Glad I could help!
 
Actually, it leaves me with the problem, that I can't level for this equipment now. Because it's 0% efficient, Omniplan thinks, it's no problem to schedule tasks to this equipment simultaneously.
How can I overcome this?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Leveling with unavailable equipment slondike OmniPlan General 0 2011-02-08 05:28 PM
Doesn't seem to be taking availability of equipment into account kdmckenzie OmniPlan General 0 2010-02-20 01:50 PM