Hi,

I have an issue I can't seem to figure out that keeps on blocking my further usage of OP in a project, I guess it's more of a lack of understanding issue than bug, here's the deal:

1. I have a list of tasks I need to do and they have each been estimated effort wise, just like here: http://cl.ly/image/3C1j1q0a452u

2. I assign resources to the tasks and they are automatically laid out to account for the resource load (as expected): http://cl.ly/image/2G2H2j2Z201N

3. I mark a task as complete, I would expect the task to be marked as completed (which indeed happens), however I'm not expecting the whole project plan to move forward (as if that task I just marked never existed) http://cl.ly/image/2Y3V362H143K

How can I prevent the tasks from readjusting after I complete them?

Best,
Kacper
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Completing actions... StevenMay OmniFocus for iPad 3 2011-10-07 10:25 PM
'Completing' a Folder lonestarg OmniFocus 1 for Mac 1 2008-03-12 10:10 PM
Are my tasks auto-completing?! Frosty Crunch OmniFocus 1 for Mac 3 2007-10-10 10:18 AM
Auto Completing Projects BwanaZulia OmniFocus 1 for Mac 16 2007-09-06 09:56 AM
Multiple Completing of Tasks SpiralOcean OmniFocus 1 for Mac 0 2007-04-30 07:57 PM


All times are GMT -8. The time now is 03:45 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.