Priority only affects Resource allocation? Thread Tools Search this Thread Display Modes
The manual says: "If two tasks are assigned to one resource at the same time, the task with higher priority gets to use the resource first."

Is that the only effect Priority has? I was hoping that via Leveling, it would push tasks with higher priority closer to the present date.
 
Yes, that's what it means. When you level, if two tasks require the same resource (and don't have other constraints affecting their schedule), the task with the higher priority will be scheduled earlier (closer to the present date).
 
(If the tasks don't share a resource, then they'll both be scheduled as early as possible, and there's no reason to consider their priorities.)
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Question about weekly meeting and resource allocation KatieUW OmniPlan General 1 2013-02-14 12:18 PM
Graphing resource allocation for multiple projects - recommendations? jbkendrick OmniPlan General 2 2009-06-10 06:16 PM
Changing resource allocation over time? TimothyMDean OmniPlan General 2 2008-09-19 05:19 AM
Resource allocation report?? gunnarlr OmniPlan General 1 2007-12-17 11:13 AM
Tracking Actual Resource Allocation. Fritz Willy OmniPlan General 1 2007-09-14 02:52 PM


All times are GMT -8. The time now is 07:18 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.