Is this possible to assign resource to a Parent(known as group in OmniPlan) task directly? When i try to assign resource to a group OmniPlan assigns it to each task in group, it's very strange behavior.
In MS Project I can assign different resources to parent and to children tasks, it is very useful, especially when you have parallel children tasks.
OmniPlan is just amazing, but I can't use it without this feature.
Any Idea?