task that takes 3 hours but I have a week to do? Thread Tools Search this Thread Display Modes
not specifically for omniplan, but I dont know how to setup a task.

Lets say I have a task that takes me 2 hours to complete, and I can do it anytime in the next 4 days. How do I represent that in ominplan? Right now, I choose 2 hours for effort or duration, but the start and end dates are wrong, or I choose start and end dates and the effort is 4 days.
 
Set up the task's duration as 2 hours, and add an end constraint* for the deadline. The start and end dates are wrong. Why are they wrong? If they're wrong because you're not working on this project for the next couple days, then you should tweak either your work schedule or the project schedule in the calendar view.
If they're wrong because you're working on other tasks for this project first, then you should add those tasks to the project and level, so that OmniPlan can calculate when you actually will get to this task.
You can also use 'reschedule' as the project progresses, to bring incomplete tasks up from the past automatically.

*Often, adding an end constraint is a sign that you've actually left another task or milestone out of your project. Why does this task need to be done in the next four days? If it's so that you can get on to the next phase of the project, a finish->start dependency might be more appropriate. An externally imposed deadline maybe should be a milestone.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
One task, two resources, different hours Bridgeblox OmniPlan General 8 2013-03-15 02:57 PM
Split a task in some hours per day lollo17 OmniPlan General 0 2011-04-22 07:01 AM
Allocating Resource to Task by Hours nitrobin OmniPlan General 0 2008-02-15 09:10 AM
hours per day? days per week? fudster OmniFocus 1 for Mac 5 2007-12-19 04:45 AM
Display hours next to task in resource view? paulwelty OmniPlan General 1 2007-10-19 11:08 AM


All times are GMT -8. The time now is 03:58 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.