Hi all

I'm evaluating omniplan for my work and started a test project.
I created a few resources (3 employees and 1 "tool" which is actually a conference room). The conference room is only available on mondays so I changed the availability to mondays only in the calendar view.
I assigned a few tasks to this resource and thought omniplan would schedule these tasks to mondays only but it's not. Looks like it doesn't care what's set in the availability for this resource?
Would be great if someone could help me with this, I'm probably doing something wrong?

Thank you

olivero
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Show/hide assigned ressource type stephaneg OmniPlan General 0 2013-05-09 12:33 PM
New task without any schedule Maxi OmniPlan General 0 2011-04-15 06:06 AM
Daily Schedule? popcornflix Applying OmniFocus 12 2010-12-12 08:01 AM
How to schedule for weekday's only matthew.e OmniFocus 1 for Mac 5 2009-04-08 10:47 AM
Schedule: As LATE as possible? wlbentley OmniPlan General 1 2006-09-12 05:34 PM


All times are GMT -8. The time now is 06:58 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.