I have a number of projects that deliver capability in phases. The phases share some preliminary common dependencies but then split off to two delivery milestones.
The current critical path highlights activities in phase 2 as critical path, but I would like to know within the project what are the critical path items leading to phase 1. At the moment I would have to delete all of the phase 2 activities, but would rather keep on project plan for both phases given the common dependencies.
The current critical path highlights activities in phase 2 as critical path, but I would like to know within the project what are the critical path items leading to phase 1. At the moment I would have to delete all of the phase 2 activities, but would rather keep on project plan for both phases given the common dependencies.