Dependencies: Start A if either B or C finishes. Thread Tools Search this Thread Display Modes
Is there a function to start an activity when either 1 out of 2 (or more) possible prerequisites have finished?

Or is there a workaround to model this situation indirectly?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Task Dependencies - Must start at commencement of another task matthewforsyth OmniPlan for iPad 2 2013-03-27 02:19 AM
Set or defer dates from Launchbar: start=start+3d; due=start+2w etc. RobTrew OmniFocus Extras 1 2011-08-08 01:15 PM
OUIEditableFrame dependencies tommetge Omni Frameworks 2 2010-08-06 07:28 AM


All times are GMT -8. The time now is 11:04 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.