Hi,
At some stage within a project, we need to wait for client feedback. I believe you need to create a hammock task for this.
However, during (re)scheduling this hammock task can get a duration of zero hours. Which means no time for feedback at all. Since it's a hammock task, I can't enter any duration.
I would like to create a hammock task with let's say a minimum duration of 1 day.
Is this possible? Or should I use another method?