The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Search Today's Posts Mark Forums Read

 
Overlap with dependent tasks Thread Tools Search this Thread Display Modes
When using Microsoft Project I could set one task with a duration, for example 2 weeks. I could then set another task as dependent on that one but specify that it was due to start part way through the other... [task1 FS - 1week].. (task 1's finish date minus 1 week).

How can I do this in Omni Plan? How can I specify overlapping tasks that are also dependent tasks?

Thanks //:)
 
I answered a similar question here: http://forums.omnigroup.com/showthread.php?t=13833
but I'll also do yours as an example.

 
Awesome, that works! Thanks // :)
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Quick way to insert new task between dependent tasks? joshfree OmniPlan General 6 2012-07-03 05:25 AM
tasks dependent on 2 resources avaliability Gizmo OmniPlan General 3 2010-11-08 09:28 PM
Automatically Shifting Dependent Tasks? Aldaron OmniPlan General 7 2010-09-21 12:00 PM
Dependent Tasks Haynes OmniFocus 1 for Mac 6 2010-03-13 03:01 AM
Request for "dependent tasks" Shanana OmniFocus 1 for Mac 6 2007-08-20 02:39 AM


All times are GMT -8. The time now is 03:59 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.