At my company, the project manager is usually working on 2-3 projects at a time. I'd like to be able to track this on the individual project plans.

I'm thinking I could create a single task "Manage Project" and assign the PM to this at 30% (or whatever). Is there a better way?

How would I make this task run the entire duration of the project, even as the duration may change? For example, if the project is late by 2 weeks, this adds 2 weeks of the developer, plus 2 weeks x 30% of the PM, something like that.

Thanks for your suggestions.
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Tracking Time, How to let staff report their time and get that data into OmniPlan? girgen OmniPlan Extras 7 2012-07-06 11:54 AM
Time Tracking? duotone OmniOutliner 3 for Mac 6 2009-12-14 10:03 PM
Time Tracking DennisHouston OmniFocus 1 for Mac 2 2009-12-01 02:22 PM
Time Tracking in OF zero OmniFocus 1 for Mac 2 2008-06-24 05:47 AM
time tracking mattao OmniPlan General 0 2007-06-11 12:21 PM


All times are GMT -8. The time now is 09:49 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.