Problem scheduling backward from fixed end Thread Tools Search this Thread Display Modes
Prev Previous Post   Next Post Next
I can't figure this out. If I schedule my project forward from a fixed start 12/10/12, it ends 1/25/13. However, I really want to launch on 1/28/13 and push things back a bit. I figure that scheduling backward from a fixed end (1/28/13) is what I should do. However, when I change the project to this setting, the project creates a violation and the project ends on 2/11/13. For some reason it pushes back the project start date to 1/7/13. I don't have any constraints and it shouldn't be a resourcing issue.

Anyone have thoughts on what is happening?
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
"Backward from Fixed End" Broken? Cowgirl OmniPlan General 0 2013-03-04 02:34 PM
Resource Availability and Scheduling Problem caj001 OmniPlan General 0 2012-07-09 05:04 PM
Scheduling Problem glasside OmniPlan for iPad 1 2012-06-08 03:14 PM
Interesting (to me) scheduling problem, really want to use OP tingham OmniPlan General 0 2009-10-15 10:20 PM


All times are GMT -8. The time now is 12:04 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.