Rescheduling uncompleted work... Thread Tools Search this Thread Display Modes
So I am new to OmniPlan. I have used several tools in the past, but like the simplicity of omniplan. One critical feature I cannot figure out how to do is to reschedule the work on a task that is incomplete when there is completed % entered on the task...

Example: I have a task "Do Stuff", this task was originally scheduled for a duration of 10 days, on 5/5/08 - 5/16/08. 50% of the task is complete (5 days completed), and I want to reschedule the remaining 50% for past the current date, so ideally it would fall from 5/21 - 5/27 (5 days work left). However, when rescheduling in OmniPlan it moves the whole 10 day task.

Now it does not show work in the resource view for the completed part, it it includes it as part of the leveling so no other work is assigned for the completed part.

This causes several holes in the plan from a work perspective when updating the plan and rescheduling uncompleted work.

Any suggestions?
 
The ability to chop the task into chunks is one of our feature requests. It's already been discussed on the forum here: http://forums.omnigroup.com/showthread.php?t=7967

If you use rescheduling to move the task, OmniPlan will not count the completed portion when leveling other tasks. However, you do need to re-level the project. OmniPlan will not re-calculate leveling (and move other tasks into the same time span as the completed portion of the task) until you click the "Level" button again.

If it still doesn't behave as you expect, you may want to send us an email with a screenshot or sample file of the behavior you're seeing.
omniplan@omnigroup.com
 
 


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Backdating completed tasks (esp. after rescheduling/leveling) omnibob OmniPlan General 1 2013-02-08 08:34 PM
How to handle uncompleted tasks in recurring projects? Zettt Applying OmniFocus 4 2012-12-14 05:32 AM
One OF database for all work or 3 for Test, Privat and Work jochen OmniFocus 1 for Mac 10 2008-07-10 09:46 AM
Rescheduling a group of tasks kwispel OmniPlan General 3 2007-12-17 02:09 PM
Rescheduling the Entire Project p_davis OmniPlan General 16 2007-12-17 11:02 AM


All times are GMT -8. The time now is 03:22 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.