The Omni Group
These forums are now read-only. Please visit our new forums to participate in discussion. A new account will be required to post in the new forums. For more info on the switch, see this post. Thank you!

Go Back   The Omni Group Forums > OmniPlan > OmniPlan General
FAQ Members List Calendar Today's Posts

 
Resource start date Thread Tools Search this Thread Display Modes
Hi there

How can i fix a resource so that it doesn't start until a certain date in the project (I speak of the human kind)?

I have a task breakdown for these people, but it's not reflecting accurately because I can not fix the date they are dues to start which is a few months ahead.

Thanks

chat-noir
 
If you flip to the "calendar" view mode, you can select the resource(s) in question, then select "Work schedule for <resourcename>" above the calendar in the lower left corner. Delete the green availability blocks from the calendar until the date that the resource becomes available for use. OmniPlan shouldn't attempt to schedule its use until that point. I agree that this is a tedious operation if the start date is a long time in the future!
 
 




Similar Threads
Thread Thread Starter Forum Replies Last Post
Start date, Forecast Workarounds for missed start dates rdbot Applying OmniFocus 8 2013-04-04 12:56 PM
Making Start Date, Due Date, Estimate Default jessicatmt OmniFocus 1 for Mac 1 2012-08-06 01:23 PM
Adding Resource Changed End Date workinprogress OmniPlan General 4 2009-10-04 12:51 PM
Problem with repeat when start date and due date exist SpiralOcean OmniFocus 1 for Mac 2 2008-09-05 04:43 AM
Sorting Columns by start date/end date/cost ..etc mr_projects OmniPlan General 5 2008-05-19 03:03 PM


All times are GMT -8. The time now is 12:50 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.